How Long Does A Custom Plan Take?

by | Jun 30, 2023

Short answer— longer than you might think

 

New clients often come through our door around May or June, asking about starting a new build during the spring. However, many of these clients don’t anticipate a long pre-build timeline.

 

On average, we allow for a 6-8 week gap for permitting and engineering plans (that is AFTER the plans are complete). So, the big question is— how long will it take to design the blueprints for a custom build?

 

To be completely transparent, it usually takes approx. 5 months. Sometimes we’ll finish a project a little faster; other times it will take a little longer. It can vary based on the individual; if you make confident, quick decisions, and know what you’re looking for, it may take less time than someone who needs to process their choices before committing.

Even if you consider yourself a great decision-maker, you may need to take extra time to accommodate so your spouse feels comfortable. A custom build is a big undertaking, and feeling rushed doesn’t typically inspire confidence.

Why does it take so long?

If you had a builder with a handful of pre-drawn, “customizable” plans, it probably wouldn’t take as long. Tweaking a plan, likely built many times before, is much faster than starting from scratch. However, we want to create a space that will fit you like a glove, a space that addresses all your family’s issues, and feels truly custom.

 

A true custom build is something that’s designed uniquely for you. Even if you look at other plans for inspiration, custom should mean that you approve of every detail. Everything should be exactly as you want and suited to your specific needs. It’s not just slightly different from the house down the street. 

 

For this reason, we encourage everyone to err on the side of allowing themselves more time through the design process. As I covered earlier— feeling rushed does not inspire confidence. Going through the design/build process should be enjoyable; no one has fun when stressed and overwhelmed.

 

The real answer? 

We often schedule our build starts 9-12 months out. We have a predetermined number of construction slots yearly to ensure we don’t get overbooked. It allows us to give every project the attention it deserves, manage every job effectively, and provide each client with a fantastic building experience.

If you come to us early, we can pencil you into a construction slot and create a design schedule to make sure your build starts on time. 

Big decisions take time, and you’ll never regret giving yourself extra for your dream design. What’s the worst that could happen? You’re ready 2 months early; you can relax and feel confident waiting to start your build!

 

If you haven’t signed up for our email series yet, make sure to do so below.
These emails will take you through a step-by-step guide of the building process, so you can be fully informed and prepared for your upcoming build.

Related Articles

Your 2025 Guide to the Best Home Heating System

Your 2025 Guide to the Best Home Heating System

Why do heating systems matter? Choosing the right heating system is crucial when building a new home or cottage in Manitoba, as heating can greatly impact both comfort and long-term costs. As energy prices rise, choosing an efficient system becomes increasingly...

How to Pick Out the Architectural Designs for My House

How to Pick Out the Architectural Designs for My House

Choosing the architectural design for your home is an exciting journey that sets the tone for your living experience. Your home should not only reflect your personal style but also meet your functional needs. Here are some essential steps to guide you through the...

Fall Home & Cottage Preparations

Fall Home & Cottage Preparations

As the days grow shorter and temperatures drop, it's crucial to prepare your home for the colder months ahead to avoid potential headaches down the line. Neglecting these essential steps could result in costly damage or a crisis when winter hits in full force. At Pine...

Can you Start a Custom Build Mid-winter in Manitoba?

Can you Start a Custom Build Mid-winter in Manitoba?

Can you start a custom build in the middle of a Manitoba winter? Absolutely! This is a conversation we frequently have with our clients. Many people associate construction with the summer months, likely because that's when roadwork tends to disrupt our commutes....

8 Ways to Design a Welcoming, Soulful Kitchen

8 Ways to Design a Welcoming, Soulful Kitchen

The kitchen is more than a space for cooking—it's where life happens. It's where you teach your children to bake their first cookies, where family stories are shared over preparing dinner, and where a simple act like making a cup of tea becomes a moment of quiet...

Message Us

Get In Touch Below. Ask Any Question or Set Up a Free Consultation

         

Office Location

904 Redonda Street,  Sunnyside, MB 

Phone

(204) 654-9888

Email

josh @pinecreek.ca

A proud member of these associations

APB
CMB
COR
CSAM
MBA